Lamesa 2 - Maynilad

  • Client: Maynilad Water Services Inc.
  • Name: Rehabilitation, Retrofitting and Process Improvement of Lamesa 2 Water Treatment Plant
  • Theme: Asset Management, Process Improvement, Retrofitting, Rehabilitation
  • Scale: 900 MLD
  • Timeline: Engineering (Jun/2016-Dec/2016), Procurement and Bidding (Aug/2016-Sep/2017), Construction (Oct/2017 onward)

Objectives

  • Upgrade the existing Pulsator WTP (900MLD) to cope with
    • High turbidity events in raining seasons (e.g. NTU up to 2000);
    • Slow performance of Sludge Extraction System under high turbidity events;
    • Rapidlly deterioration and corrosion of structures and assets;
    • 7.2 magnitute of earthquake.
  • Provide better integration and connectivity with the Lamesa 1 Water Treatment Plant (1200 MLD) and the Sludge Treatment Facility (STF) being designed and constructed by JFE Contractor.
  • Provide fully Automation and integration (e.g. SCADA)

Roles and Responsibilities

  • Project Management

Lesson Learned

Authorship

Back to Projects

Avatar
Lê Thanh Nam
Kĩ sư đánh giá rủi do, quản lý dự án xây dựng, quản lý các hệ thống kĩ thuật nhà máy và công trình

Nghiên cứu và ứng dụng vận trù học, toán tối ưu, xác xuất thống kế trong việc quản lý và vận hành các hệ thống tài sản kĩ thuật và công trình.

Sau
Trước